  • By completing this form, you confirm that we may contact you via email, that you are over the age of 16 and that we can send you periodic emails, containing useful and interesting information including our email newsletter. Please see our privacy policy for more information and to see how you can manage your consent.

  • Fields marked with an * are mandatory

ecco
Previous case study

TABLET MANUFACTURING SUITE HEATING, VENTILATION AND AIR CONDITIONING SYSTEM UPGRADE

Client: Global pharmaceutical manufacturer | Location: Cape Town | Sector: PHARMACEUTICAL MANUFACTURING

Download

Find out more

Previous case study

PROJECT BRIEF

EECO2 was asked to assist in reducing energy demand at a tablet manufacturing facility without compromising product quality or regulatory compliance. Challenges included:
  • High volumes of fresh air requiring dehumidification in very challenging ambient conditions
  • Adapting the HVAC system to meet current manufacturing requirements
  • Reducing the volume of the dust extraction system and install VSD
  • Initiating no operational setbacks.

SOLUTION

Our work included:

Install a fresh air cooling coil to eliminate dehumidification within the air handling unit (AHU)

Rebalance the areas dust extraction system to eliminate nozzles no longer required

Install a VSD onto the dust extraction unit to maintain pipework carrier velocity consequently enabling a reduced fresh air volume

Rebalance the Air Change Rates to reflect area manufacturing change of use.

Initiate non-operational air volume reductions.

Optimise BMS system.

Product risk assessments were developed with the site QA, production & engineering team.

Risk mitigation was evaluated and included where required.

Final design changes reflected a risk averse approach.

CLIENT TESTIMONIAL

It’s going to be a tough year and to know that we have such a good team supporting some of these changes makes the job a lot easier.

Manufacturing Support Manager

Global pharmaceutical manufacturer

RESULTS

Energy savings (per year)

Energy savings (per year)

363,000 kWh

Energy cost savings (per year)

Energy cost savings (per year)

£36,000

Emissions reduction (per year)

Emissions reduction (per year)

336 tonnes